Rudder
Progress has been slightly hindered for 3 days by a defective gelcoat spray gun but after a fix all is back to full speed in the composite build. As Andrew is fairing the rudder plug the stbd. deck mold is transported back to the assembly building where the deck has already been finished. The keel and bowsprit molds are being prepared for layup. Generator and many deck parts are starting to arrive and the two Yanmar engines will be delivered early this week.